Project Updates
UNDERSTAND WHAT YOU ARE INVESTING IN

ONE18 Residences

STAGE 1
Site Work & Foundation






one18 site preparation






































one18 first bore pile done




















one18 boarding in progress




















Setting up concrete pump and casting pipe inside bore pile














Inserting pipe for casting, checking slump and casting









Extracting hose after flushing base of bored hole A5




Checking depth and cage for C63




Checking C63 cage before placing into bored hole


Casting of A5




STAGE 1 - Posted on 29 August 2016
Site Work & Foundation


Leveling the ground


Leveling the ground


Leveling the ground


Leveling the ground


Leveling the ground

STAGE 1 - Posted on 27 October 2016
Site Work & Foundation


Soil excavation & removing of existing CBP at 3.00m


Soil excavation & removing of existing CBP at 3.00m


Soil excavation & removing of existing CBP at 3.00m


Soil excavation & removing of existing CBP at 3.00m


Soil excavation & removing of existing CBP at 3.00m


Soil excavation & removing of existing CBP at 3.00m

STAGE 1 - Posted on 28 November 2016
Site Work & Foundation


Soil excavation for 2nd layer and completion 85% up to date


Soil excavation for 2nd layer and completion 85% up to date


Soil excavation for 2nd layer and completion 85% up to date


Soil excavation for 2nd layer and completion 85% up to date


Soil excavation for 2nd layer and completion 85% up to date

STAGE 1 - Posted on 19 December 2016
Site Work & Foundation


Soil excavation for 3rd layer


Soil excavation for 3rd layer


Soil excavation for 3rd layer


Soil excavation for 3rd layer


Soil excavation for 3rd layer


Soil excavation for 3rd layer


Soil excavation for 3rd layer


Soil excavation for 3rd layer

STAGE 1 - Posted on 17 January 2017
Site Work & Foundation


Layer four excavation


Layer four excavation


Layer four excavation

STAGE 1 - Posted on 20 February 2017
Site Work & Foundation


Installing bracing for shoring at 5th level


Installing bracing for shoring at 5th level


Soil excavation and pile head breaking at 5th level - 95% completed


Team briefing


Team briefing

STAGE 1 - Posted on 20 March 2017
Site Work & Foundation


Existing contiguous bored pile (CBP) breaking


Existing contiguous bored pile (CBP) breaking


Existing contiguous bored pile (CBP) breaking


Existing contiguous bored pile (CBP) breaking


Existing contiguous bored pile (CBP) breaking


Existing contiguous bored pile (CBP) breaking


Existing contiguous bored pile (CBP) breaking


Existing contiguous bored pile (CBP) breaking

STAGE 1 - Posted on 17 April 2017
Site Work & Foundation


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap


Reinforcements bar installing for basement cap

STAGE 1 - Posted on 26 May 2017
Site Work & Foundation


Casting basement


Casting basement


Casting basement


Casting basement


Casting basement


Casting basement


Casting basement


Remove shoring support


Remove shoring support


Remove shoring support


Remove shoring support


Water curing


Water curing


Water curing


Water curing


Water curing

STAGE 1 - Posted on 23 June 2017
Site Work & Foundation


Basement 3 slab


Basement 3 slab


Basement 3 slab


Basement 3 slab


Basement 3 slab


Basement 3 slab


Basement 3 slab


Basement 3 slab


Basement 3 slab


Basement 3 slab


Installing formwork and rebar


Installing formwork and rebar


Installing formwork and rebar


Installing formwork and rebar


Installing formwork and rebar


Installing formwork and rebar


Installing formwork and rebar
STAGE 1 - Posted on 19 July 2017
Site Work & Foundation


Casting concrete for basement 3's zone A retaining wall


Casting concrete for basement 3's zone A retaining wall


Casting concrete for basement 3's zone A retaining wall


Casting concrete for basement 3's zone A retaining wall
STAGE 1 - Posted on 31 August 2017
Site Work & Foundation


Installing the formwork and rebar for basement B1 slab floor


Installing the formwork and rebar for basement B1 slab floor


Reinforcements bar and formwork installation for Basement slab floor 1 zone A 100% completed


Reinforcements bar and formwork installation for Basement slab floor 1 zone A 100% completed


Basement 1 zone casting 100% completed


Basement 1 zone casting 100% completed


Basement 1 zone casting 100% completed


Basement 1 zone casting 100% completed


Formwork and rebar installing for column and core wall of basement B1


Dismantling shoring system level-A complete 30%


Rebar and formwork installing for column of basement B1 complete 40%


Rebar and formwork installing for core wall and column B1


4 columns at basement B1 zone B proceeding to cast concrete


Installing the rebar and formwork for column and core wall at basement B1 zone A


Dismantling the working duct


Rebar and formwork installing for B1 zone A


Rebar and formwork installing for retaining at Basement 1 Zone A


Formwork and reinforcements bar installation for ground floor (GF) slab


Installing formwork and supports for ground floor (GF) slab floor Zone A and Zone B


Formwork and reinforcements bar installation for retaining wall of Basement 1 Zone A and Zone B


Formwork and reinforcements bar installation for retaining wall of Basement 1 Zone A and Zone B


Concrete casting - Column B1 zone A


Concrete casting - Car lift wall at B1 zone A


Concrete casting - Core wall at B1 zone A


Concrete casting - Column B1 zone B

STAGE 1 - Posted on 26 September 2017
Site Work & Foundation


Water curing for fresh concrete and cleaning for column ground floor


Water curing for fresh concrete and cleaning for column ground floor


Erecting 1st floor slab formwork


Erecting 1st floor slab formwork


Inspection on ground floor main column rebar prior closing formworks


Inspection on ground floor main column rebar prior closing formworks


Preview from 1st floor level


Erecting rebar at grid line L column


Erecting rebar at grid line L column


Backfill on going at grid line L edge of building


Backfill on going at grid line L edge of building


Install rebar at passenger lift wall


Install rebar at passenger lift wall


Install rebar at passenger lift wall


Install rebar at passenger lift wall


Erecting 1st floor slab formwork at grid line G,H,J


Erecting 1st floor slab formwork at grid line G,H,J


Installing rebar at passenger and service lift core wall


Installing rebar at passenger and service lift core wall


Installing rebar at passenger and service lift core wall


Closing formwork at column AB1 and preparing for casting


Casting for ground floor column at zone A


Casting for ground floor column at zone A


Casting for ground floor column at zone A


Casting ground floor column at grid line AB1 , KL1


Casting ground floor column at grid line AB1 , KL1


Installing rebar at grid line AL1


Installing rebar at grid line AL1


Checking and tightening lift core formwork prior casting


Install rebar on going at 1st floor slab.


Install rebar on going at 1st floor slab.


Casting staircase and lift core wall


Casting staircase and lift core wall


Casting staircase and lift core wall


Night shift works on rebar installation


Night shift works on rebar installation


Preview on 1st floor slab.


Preview on 1st floor slab.


Preview on 1st floor slab.


Tidy up rebar and cleaning formworks prior inspection continue with casting concrete


Tidy up rebar and cleaning formworks prior inspection continue with casting concrete

STAGE 1 - Posted on 25 October 2017
Site Work & Foundation


Installing MEP pipe sleeve at floor slab


Installing MEP pipe sleeve at floor slab


Installing slab bottom layer slab rebar


Installing slab bottom layer slab rebar


Works continue through the night


Works continue through the night


Installing upper layer slab rebar


Installing upper layer slab rebar


Installing drop floor formwork (toilet area)


Installing drop floor formwork (toilet area)


Panorama view at 2nd floor slab preparation prior casting


Concrete casting continued at night


Concrete casting continued at night


Concrete curing after night casting at 2nd floor slab


Concrete curing after night casting at 2nd floor slab


Installing rebar at 2nd floor lift core wall


Installing rebar at 2nd floor lift core wall


Panorama view for rebar works at 2nd floor column and lift core wall

STAGE 1 - Posted on 24 November 2017
Site Work & Foundation


Preparation prior concrete casting at 3rd floor slab


Casting on 3rd floor slab


Hoisting and mobilize formwork material for 4th floor slab


Hoisting and mobilize formwork material for 4th floor slab


Concrete curing and erect column rebar


Panorama view at 3rd floor column formworks installation


Install table formworks for 4th floor slab


Installing 3rd floor lift core wall system formworks


Night casting on column


Elevated view on 4th floor formworks installation


Install slip form and table form for 3rd floor lift core wall and slab


Install 4th floor slab formworks


Install slip formworks for 3rd floor lift core wall and 4th floor slab rebar


Works continue at night shift


Panorama view on 4th floor slab formworks


Panorama view at 3rd floor slip form installation


Install rebar for 4th floor slab


Overview on 4th slab


Concrete casting for lift core wall


Installing lift core wall rebar


Preparation and cleaning prior concrete casting


Night casting on 4th floor slab


Night casting on 4th floor slab


Panorama view at 4th floor level


Install 4th floor column rebar at Grid Line A1


Installing column formworks and slip form rebar


Installing column formworks and slip form rebar


Overview on 4th lift core wall casting


Concrete casting for 5th floor lift core wall and column


Elevated view on 5th floor slab installation

STAGE 1 - Posted on 28 December 2017
Site Work & Foundation


Installing 7th floor slab table formworks


Installing 7th floor slab formworks


Installing top layer rebar at 7th floor slab


Lightweight block for mockup at 2nd floor





Installing rebar at 7th floor balcony area


Overview on 7th floor rebar works


Setting out line for brickworks at 2nd floor


Casting on progress at 7th floor



Casting at 7th floor slab


Installing 7th floor rebar and column formworks


Night casting for 7th floor column and transferring slab formworks


Install block works at 2nd floor for mock up units


Casting 7th floor column (second portion)


Casting 7th floor column (second portion)


Install light weight block for mockup at 2nd floor


Installing rebar at 8th floor slab


Installing clay brick for mock up units at 2nd floor


Overview on 2nd floor mock up units


Mock up units progress at 2nd floor


Preparation prior casting at 8th floor slab





Installing 8th floor column formworks


Concrete casting for 8th floor column


Installing rebar at 9th floor slab


Night works continue 9th floor slab formworks


Installing rebar at 9th floor slab


Casting 10th floor lift core wall


Continue to install rebar for 9th floor slab, target to cast on Friday.


Installing rebar at 9th floor slab


Expediting rebar installation prior casting

STAGE 2
Superstructure

COMING SOON!

STAGE 3
Finishing Works

COMING SOON!

STAGE 4
TOP & Handover

COMING SOON!

Sitemap
Top

Announcement

FundHive is pleased to announce our collaboration with SeedIn Technology Pte Ltd.

SeedIn is an innovative peer-to-peer financing platform licensed by the Monetary Authority of Singapore. All FundHive members will be invited to sign up for membership and updates from SeedIn Technology. This partnership will allow us to explore new and innovative ways to better serve our members. Please keep a lookout for our EDM in your mail inbox for more details!