Project Updates
UNDERSTAND WHAT YOU ARE INVESTING IN

Tavistock

STAGE 1
Site Work & Foundation

A general summary of the work being done in this stage includes:

• Tearing down of House Front
• Removal of Internal Fittings (Windows, Doors, Miscellaneous Debris) from Backyard, Main Hall, Bedrooms and Balcony
• Removal of Awnings from Frontage
• Work and Removal on both Sidewalls
• Haulage Trunk in place to collect Debris
• Other Miscellaneous Work



House Front - Tearing Down in Progress


Main Hall - Removed Windows and Hall


Bedroom - Removed Doors and Windows


Sidewall - Plants & Glass Partion removed


Frontage - Haulage Truck to collect debris


Frontage - Removed Awnings



Ground preparing




STAGE 2 - Updated on 29 August 2016
Superstructure


Brickworks


Brickworks


Brickworks


Exterior Construction Update


Exterior Construction Update


Front Porch


Roof Top


Roof Top

STAGE 2 - Updated on 16 September 2016
Superstructure


Brickworks


Brickworks


Brickworks


Brickworks


Brickworks


Brickworks


Brickworks


Brickworks


Exterior Construction


Exterior Construction


Installing Piping


Sanitary Works


Sanitary Works

STAGE 2 - Updated on 27 October 2016
Superstructure


Architect Work


Architect Work


Architect Work


Architect Work


Architect Work


Architect Work


Architect Work


Exterior Outlook as of 26 October 2016

STAGE 2 - Posted on 28 November 2016
Superstructure


Interior Design Stage


Interior Design Stage


Interior Design Stage


Interior Design Stage


Interior Design Stage

STAGE 2 - Posted on 19 December 2016
Superstructure


Carpentry Delivery


Carpentry Delivery


Carpentry Delivery


Overview


Overview


Overview

STAGE 3 - Posted on 17 January 2017
Finishing Works


Finishing Works


Finishing Works


Finishing Works


Finishing Works


Floor Finishing Works


Floor Finishing Works


Overall Finishing Works


Wardrobe Finishing Works

STAGE 4 - Posted on 20 February 2017
TOP & Handover


TOP (Temporary Occupation Permit) Obtained


TOP (Temporary Occupation Permit) Obtained


TOP (Temporary Occupation Permit) Obtained


TOP (Temporary Occupation Permit) Obtained

Sitemap
Top

Announcement

FundHive is pleased to announce our collaboration with SeedIn Technology Pte Ltd.

SeedIn is an innovative peer-to-peer financing platform licensed by the Monetary Authority of Singapore. All FundHive members will be invited to sign up for membership and updates from SeedIn Technology. This partnership will allow us to explore new and innovative ways to better serve our members. Please keep a lookout for our EDM in your mail inbox for more details!