228 Oknha Peich

STAGE 1
Site Work & Foundation

We have successfully completed the foundation stage and are progressing to the construction of super structure from ground level onwards.

A general summary of this stage includes

• Pre-survey of ground including geological and soil investigation, topography & boundary survey
• Demolition of the old existing building
• Construction of temporary boundary walls and levelling of site ground
• Mobilization of workers
• Construction of retaining walls and bore piles, load tests, excavation works
• Casting of basement slabs and columns up to ground level
• Etc.

One of the challenges we faced included downpour from the rainy season heavier than expected. However we were able to manage our work force and schedule efficiently to speed up site activities while keeping safety the utmost importance at our site premises.



Casting of Bore Pile


Preparing Rebar cage for bore pile


Coring of Bore pile


Excavation in progress


Load Test


Rig on site for construction of retaining wall & Bore Pile


General view of basement, installing rebar & Waterproofing


Pump truck & Concrete pump in action


Casting of Basement ground


Casted Basement ground slab


Casted Basement staircase
STAGE 2
Superstructure

In this stage of construction, we are focused on the following scope of works:

• Structural works including columns and slabs from ground level up
• Brickwork including walls and floors
• MEP services such as electrical, MVAC, life & fire system
• Plumbing & Sanitary works

Safety has always been a core consideration at our construction site. We conduct tool box meeting regularly to remind and educate our construction team on the importance of safe practices.



Rebar work for columns from ground level


Form work for columns from ground level


Casted columns from ground level


Preparing Rebar & Form work for ground slab for mezzanine level


Casting for ground slab for mezzanine level


Toolbox Meeting


Site Inspection


Dismantling side formwork at Passenger Lift the day after casting


Dismantling side formwork of Passenger Lift the day after casting


Washing and cleaning new Slab the day after casting to commence erection of Column Formworks


0F Level - Final fastening of wire tie to secure Rebar arrangement and also clean-up prior to casting


0F Level - Final fastening to secure Rebar arrangement with wire ties and also clean-up prior to casting


0M Level - Manual Troweling with aluminum horizontal bar to achieve consistence flatness as well as to the required Slab top finishing level


0M Level - Casting of Floor Slab at Dining Area of Mezz Restaurant


1F Level - Water curing on the newly casted RC Slab


1F Level - Another view on water curing of newly casted RC Slab


1F Level - Workers spreading out the fresh concrete and using electrical vibrator to eliminate air pockets


1F Level - Casting of Floor Slab and Beam


1F Level - Casting activity towards the last end section of the building


2F Level - Casting of Floor Slab and Beam in progress


2F Level - Trowelling to level the top slab in progress


2F Level - Workers casting and troweling to level the top slab


2F Level - Workers spreading out the concrete and trowelling to level the top slab


3F Level - Casting in progress


3F Level - Final inspection and touch-up before casting starts


3F Level - Newly casted 3F level RC Slab


3F Level - Pouring of concrete via delivery pipe from Concrete Pump Truck


4F Level - Concrete Pump Truck in position with concrete delivery pipe extended to 4F Level


4F Level - Final Rebars touch-up work prior to casting


4F Level - Newly casted 4F Level RC Slab


4F Level - Pouring of concrete and trowelling to level the top of RC Slab


4F Level - Rebar works in progress


4F Level - Workers spreading and trowelling to level the top RC Slab


5F Level - Cleaning of Formworks using high pressure water jet machine


5F Level - Concrete Pump Truck delivery pipe and flexible hose fully extended to reach the back of the building


5F Level - Final inspection of Rebar works prior to casting


5F Level - Inspection of Rebar works prior to casting


5F Level - Pouring of concrete and Concrete Vibrator in progress while other workers wait to spread and trowel the surface


5F Level - Worker trowelling to level the freshly casted RC Slab


6F Level - Inspection and touch-up of Rebars work prior to casting


6F Level - Setting up the delivery pipes from the Concrete Pump that is parked at the road below


6F Level - Workers checking the surface finishing of the newly casted RC Slab


6F Level - Workers spreading and trowelling concrete to level the top RC Slab


6F Level - Workers spreading and trowelling to level the new RC Slab


7F Level - Setting up the concrete delivery pipe from the Concrete Pump parked at the road


7F Level - Workers using Concrete Vibrator during casting of fresh concrete


7F Level - Workers trowelling to level the top of the newly casted RC Slab


8F Level - Final checks for cleanliness before casting


8F Level - Inspection and touch-up of Rebar and Formworks prior to casting


8F Level - Worker trowelling to level the top surface of the newly casted concrete RC Slab


8F Level - Workers spreading and levelling the freshly poured concrete


9F Level - Casting of RC Staircase steps in progress


9F Level - Casting work in progress


9F Level - Final inspection, checks, adjustment and touch-up prior to casting


9F Level - Inspection and touch-up of Rebars prior to casting


9F Level - Surface of newly casted RC Slab


10F Level - Workers trowelling surface to level the newly casted RC Slab


10F Level - Inspection and checks of Rebar and Formworks prior to casting


10F Level - Pouring concrete from delivery pipe and flexible hose via Concrete Pump park at the road


11F Level - Inspection, checks and touch-up prior to casting


11F Level - Final checks of Rebars and Formworks prior to casting


11F Level - Pouring of concrete via delivery pipe and flexible hose from Concrete Pump


11F Level - Workers trowelling the surface to level the newly casted RC Slab






228-12F


12F Level - Final check, touch-up and cleaning before casting


12F Level - Inspection of Slab, Beam rebars and formworks prior to casting


12F Level - Workers spreading out concrete and using vibrator to cast the slab


12F Level - Workers trowelling the freshly poured concrete to level the top surface

STAGE 3
Finishing Works



Mockup AC


Ceiling For Suite Room

STAGE 3 - Updated on 29 August 2016
Finishing Works


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed


Mock up room completed

STAGE 3 - Updated on 26 September 2016
Finishing Works


Staff Office


Staff Office


Staff Office


Staff Office


Staff Office Equipment


Interior Office Lights


Glass Panel


Sky Bar Wall Finishing


Sky Bar Wall Finishing





Jaccuzi


Jaccuzi



Monitors


Server Rack


Main Distribution Board



Guestroom level corridor

STAGE 3 - Updated on 27 October 2016
Finishing Works


3F & 4F


3F & 4F


3F & 4F


3F & 4F


3F & 4F


3F & 4F


3F & 4F


Basement


Basement


Basement


Basement


Basement


Ground Floor Water Tank Cleaning


Ground Floor Water Tank Cleaning


Ground Floor Water Tank Cleaning


Ground Floor Water Tank Cleaning


Lobby Canopy


Lobby Canopy


Lobby Canopy


Lobby Canopy

STAGE 3 - Updated on 28 November 2016
Finishing Works


Front Canopy Start Installation


Front Canopy Start Installation


Front Canopy Start Installation


Front Canopy Start Installation


Front Canopy Start Installation


Rooms Completing Curtain


Rooms Completing Curtain

STAGE 3 - Updated on 19 December 2016
Finishing Works


Canopy Work at Lobby


Canopy Work at Lobby


Curtain Works


Finishing Works at Rooftop


Finishing Works at Rooftop


Gym Room Touching Up


Jacuzzi Planting Work


Jacuzzi Work in Progress


Lobby Lighting


Lobby at Level 7


Office Furniture Set Up


Reception Counter at work


Room View


Setting up of Divan Bed and Mattress


Setting up of Divan Bed and Mattress


Timber Works at Level 15

STAGE 3 - Updated on 17 January 2017
Finishing Works


Finishing Works


Finishing Works


Finishing Works


Finishing Works


Rooftop Finishing Works


Gym Finishing Works


Jacuzzi Finishing Works


Lobby Finishing Works


Lobby Finishing Works


Overall Finishing Works


Overall Finishing Works


Washroom Finishing Works

STAGE 3 - Updated on 20 February 2017
Finishing Works


Exterior View


Room 708


Room 708


Room 708


Room 805


Room 805

STAGE 4 - Updated on 20 March 2017
TOP & Handover


Exterior View


Lumiere Executive Room


Bathroom


Lobby


Gym


Rooftop Jacuzzi


Rooftop View


Sky Bar


Sky Bar


Sky Bar

Sitemap
Top

Announcement

FundHive is pleased to announce our collaboration with SeedIn Technology Pte Ltd.

SeedIn is an innovative peer-to-peer financing platform licensed by the Monetary Authority of Singapore. All FundHive members will be invited to sign up for membership and updates from SeedIn Technology. This partnership will allow us to explore new and innovative ways to better serve our members. Please keep a lookout for our EDM in your mail inbox for more details!